A well known Contractor is looking for a Project Controls Planning Manager for the Bangkok Metro project.
Project Controls/ Planning Assistant to Project Manager/Project Director as directed
The Primary Objective of Project Controls shall be to Expand in detail the Project Managers planning into using Prima Vera or MS Project &Excel Spreadsheets
1. Coordinate with all concerned parties such as the construction team, suppliers, and sub contractor to gather all & commit schedule infomation
2.Detailed Work Breakdown Structures for each of the disciplines (Design Shop Drawings, Procurement, Methods, Civil works, Buildings, Structural Concrete, Pre-Stressed Concrete, Precast Concrete, Steel Structures, Cladding, MEP, Architectural, Logistics/Transport, Equipment (monitor preventative maintenance schedules) at the Red Line project & other projects as required. These include all detailed planning for work associated with
ïƒ Shop Drawings schedules for each discipline
ïƒ Procurement schedules for each discipline)
ïƒ Civil Earthworks , Roadworks, At-Grade Drainage
ïƒ Civil Structures: Substructures: Piling/ pile Caps/ Columns, Crossbeams, Corbels
ïƒ Civil Superstructure: Viaduct, Barrier, Drainage, Bearing plinths, Bearing installation & grouting
ïƒ Precast Yard Production & Delivery Schedule
ïƒ Precast product Logistic / Transportation schedules by rail and by road
ïƒ Steel fabrication Factory production & Delivery schedules
ïƒ Steel Product Logistic/ Transportation schedules by road
ïƒ Precast Product erection schedules by Crew/by Crane/by Shift
ïƒ Steel Works: Fabrication/Transport/Erection
ïƒ MEP procurement & installation schedule
ïƒ Architectural procurement & installation schedule
ïƒ Monitor procurement schedule performance
ïƒ Resource scheduling on an as-required basis as directed by management
3.Prepare the details of each activity such as no. of work fronts, no. of labour per work front, cycle time, machinery and equipment required.
4.Explain and prepare planning ideas information of each activity to transfer to construction team
5.Monitoring all daily progress activities on job site
6.Detailed Weekly performance reports on all disciplines listed above. Identify non-performing disciplines at respective locations to generate Exception reports (non-performing disciplines)
7.Detailed Exception reports on identified non performing disciplines, with problem analysis & proposed corrective action (rescheduling to get back on program)
8.Projected Project Completion (in each discipline)
9.S-Curve preparation planned work (Budgeted) vs actual work performed (earned value)
10.Comprehensive Monthly Project Control reports on all disciplines as directed